Tamarack Lake Trail Extension Planning
This project is funded by $50K 2022-22 RTP Grant
Goal of Project
Obtain approval of a 6 to 7.5 mile extension of Tamarack Lake Trail connecting Reno/Truckee Meadows Trails with the Tahoe Basin Trails by a quality sustainable multi-use non-motorized singletrack track trail open to mountain bike use.
Scope of Project:
Establish a trail alignment for the extension of the existing 4.3 mile Tamarack Lake Trail from near Mt. Rose Ski Area Entrance to Galena Creek Park Trail Network
Obtain all relevant clearances to satisfy NEPA and land manager requirements via contracted studies to obtain categorical exclusion and approval for trail from USFS and Washoe County.
Research if area user created trails can be incorporated.